  • Tennessee Valley Authority (TVA)
    • Performed Economic (Total Production Costs) and LOLE Based Reserve Margin Studies in 2009, 2011, and 2013
    • Performed Interruptible Contract Evaluation in 2010.  Examined both Economics and Physical Reliability Metrics.
  • Duke Energy
    • Performed Economic (Total Production Costs) and LOLE Based Reserve Margin Study in 2012
  • Santee Cooper
    • Performed Economic (Total Production Costs) and LOLE Based Reserve Margin Study in 2011
  • CLECO
    • Performed Economic (Total Production Costs) and LOLE Based Reserve Margin Study in 2010
  • Southern Company
    • Performed Economic (Total Production Costs) and LOLE Based Reserve Margin Study in 2007, 2010, 2013
    • Performed Interruptible Contract Evaluation. Examined both Economics and Physical Reliability Metrics.
    • Performed Various Other Resource Adequacy Assessments and Production Cost Studies including fuel availability studies.
  • Louisville Gas & Electric
    • Performed Economic (Total Production Costs) and LOLE Based Reserve Margin Study in 2010-2011
    • Assisted in future studies and updates that utilized the SERVM Model
  • Public Service Company of New Mexico (PNM)
    • Performed Economic (Total Production Costs) and LOLE Based Reserve Margin Study in 2013
    • Performed Renewable Integration study in 2014 (ongoing)
  • TERNA
    • Performed Capacity Demand Curve Development in 2012 in cooperation with The Brattle Group
  • Electric Power Research Institute (EPRI)
    • Performed research projects studying reliability impact and flexibility requirements needed with increased penetration of intermittent resources in 2013
    • Created and Implemented a Risk-Based Planning Tool to analyze system reliability metrics in 2014
  • Federal Energy Regulatory Commission (FERC)
    • Performed Economics of Resource Adequacy Work in 2012-2013 in cooperation with the Brattle Group. Included analyzing resource adequacy from regulated utility and structured market perspective.
  • California Public Utilities Commission (CPUC)
    • Currently assisting in Effective Load Carrying Capability (ELCC) Study for the State of California
  • Eastern Interconnection States’ Planning Council (EISPC)
    • Performed Economics of Resource Adequacy White Paper in 2012-2013
    • Currently Working on Probabilistic Risk Assessment for Transmission and Other Resource Planning Work in cooperation with EPRI
  • ERCOT
    • Completed a Reserve Margin Study requested by the PUCT, examining an array of physical reliability metrics. (See Publications: Expected Unserved Energy and Reserve Margin Implications of Various Reliability Standards)
    • Performed an Economic Optimal Reserve Margin Study in cooperation with the Brattle Group (2014).  The report examined total system costs, generator energy margins, reliability metrics, and economics under various market structures (energy only vs. capacity markets)
    • Probabilistic Risk Assessment for the North American Electric Reliability Corporation (NERC) in 2014
  • Pacific Gas & Electric (PG&E)
    • Performing ELCC and Renewable Cost Integration Studies (ongoing)
    • Performing a Flexibility Requirement Study (2014)
    • Performing LTPP studies (2014)
  • PJM
    • Seasonal Reliability Assessment (2014)
  • NCEMC
    • Reliability Assessment in NCEMC’s for all of its jurisdictions (ongoing)

 

Independent Evaluator Experience

Astrapé has acted as a subcontractor to the Accion Group for many independent evaluator engagements across the country. Our expertise is in validating evaluation methodologies and results in generation capacity procurements and reporting findings back to Public Service Commissions and appropriate Staff.

  • Black Hills
    • Capacity Procurement (2014)
  • Southern California Edision (SCE)
    • Renewable Request for Offers (RAM 1-5 and SPVP 1-4) (2011-2014, ongoing)
  • Georgia Power
    • ASI Programs (2014)
  • San Diego Gas & Electric
    • Short Term Capacity Procurement (2013)
  • Portland Gas & Electric
    • Various Renewable, Base Load, and Flexible Resource Procurement (2009, 2011-2013)
  • Public Service Company of Colorado
    • All Source Procurement (2013)
  • Arizona Public Service Company
    • Renewable Procurement (2010)
  • Southwest Public Power Resources Group
    • Base Load Energy Procurement (2009-2010)

Financial Project Analysis

Astrapé has performed work in cooperation with Competitive Energy Insights to analyze financials on specific power projects that are in development. This includes but is not limited to baseload, peaking, flexible, renewable resources, and behind the meter projects. Full financial pro formas were developed with financial statements and IRR calculations as well as the inclusion of all tax treatments related to incentives. We have provided this type of work for the following clients from 2007 – 2014.

  • LCRA
  • SMUD
  • Sempra
  • ABB
  • Emcore
  • LaunchPoint